ARU's Offtake/Funding Strategy

I think in these types of performance targets, they need to give some head room for better than expected outcomes.

And given what the US is proposing to do for critical minerals (and RE)...this 75% cornerstone equity could happen.

But I have always thought....there will be a rush from the institutions, just before FID, when they realise what is really going on in the market, and how well positoned ARU is within the market to be a global leader.

Also look at what JP Morgan is proposing....spending $1.5T.....some of that will fall into ARU...

https://rareearthexchanges.com/news...iency-push-critical-minerals-quietly-central/
That pre-FID pre construction positioning is happening right now, how long will it last, well thats going to be interesting. Monday will be fun.
 
The big winners from the Australia-US critical minerals deal

Two big winners
While the deal boosted sentiment in the Australian critical minerals space, there were two big winners in Albanese’s announcement, Arafura Rare Earths (ASX: ARU) and a joint venture between Alcoa (NYSE: AA) and Sojitz Corp (TYO: 2768).

It was a double win for Gina Rinehart-backed Arafura, which also received a letter of interest (LoI) from the Export-Import Bank of the United States (EXIM) for up to $300 million of funding for its $1.2 billion Nolans project in the Northern Territory.

“I’ve never seen this level of cooperation between the tops of two governments working together in terms of matching supply and funding. It’s actually quite historic,” Arafura managing director Darryl Cuzzubbo told MINING.com from New York, where he had just completed 12 consecutive hours of investor meetings.

“Essentially, through the agreement, Australia is giving somewhat preferential treatment to its critical minerals, to the US, and in return, the US is giving somewhat preferential treatment to funding and price mechanisms, particularly funding, both on the debt and the equity side.

“And then secondly, the agreement spells out how the process can be sped up, which will allow projects to move into construction quicker than they otherwise would,” Cuzzubbo said.

Ready to build
The Australian government announced a $100 million equity investment in Arafura’s Nolans project through Export Finance Australia.

Arafura has already invested A$60 million ($39 million) in early works at Nolans.

“We’re expecting to finalize our cornerstone equity by the end of this year, and that allows us to then finalize the rest of the funding early next year and then move into construction early next year,” Cuzzubbo said.

Nolans has a three-year construction period and a two-year ramp-up phase. Once in full production, it will produce 4,440 tonnes per annum (tpa) of neodymium-praseodymium, 573tpa of mixed middle-heavy rare earths oxide and 5144,393tpa of phosphoric acid.

“You’ve got Korea, the US and Germany trying to diversify away from China. At the same time, demand is doubling,” Cuzzubbo said.

“Then you look at the rare earths supply pipeline, the number of projects that can move into construction, there’s not too many projects that are going to move into production in the next five to 10 years.”

 
The big winners from the Australia-US critical minerals deal

Two big winners
While the deal boosted sentiment in the Australian critical minerals space, there were two big winners in Albanese’s announcement, Arafura Rare Earths (ASX: ARU) and a joint venture between Alcoa (NYSE: AA) and Sojitz Corp (TYO: 2768).

It was a double win for Gina Rinehart-backed Arafura, which also received a letter of interest (LoI) from the Export-Import Bank of the United States (EXIM) for up to $300 million of funding for its $1.2 billion Nolans project in the Northern Territory.

“I’ve never seen this level of cooperation between the tops of two governments working together in terms of matching supply and funding. It’s actually quite historic,” Arafura managing director Darryl Cuzzubbo told MINING.com from New York, where he had just completed 12 consecutive hours of investor meetings.

“Essentially, through the agreement, Australia is giving somewhat preferential treatment to its critical minerals, to the US, and in return, the US is giving somewhat preferential treatment to funding and price mechanisms, particularly funding, both on the debt and the equity side.

“And then secondly, the agreement spells out how the process can be sped up, which will allow projects to move into construction quicker than they otherwise would,” Cuzzubbo said.

Ready to build
The Australian government announced a $100 million equity investment in Arafura’s Nolans project through Export Finance Australia.

Arafura has already invested A$60 million ($39 million) in early works at Nolans.

“We’re expecting to finalize our cornerstone equity by the end of this year, and that allows us to then finalize the rest of the funding early next year and then move into construction early next year,” Cuzzubbo said.

Nolans has a three-year construction period and a two-year ramp-up phase. Once in full production, it will produce 4,440 tonnes per annum (tpa) of neodymium-praseodymium, 573tpa of mixed middle-heavy rare earths oxide and 5144,393tpa of phosphoric acid.

“You’ve got Korea, the US and Germany trying to diversify away from China. At the same time, demand is doubling,” Cuzzubbo said.

“Then you look at the rare earths supply pipeline, the number of projects that can move into construction, there’s not too many projects that are going to move into production in the next five to 10 years.”

Quicker than it normally would? That’s new
 
The big winners from the Australia-US critical minerals deal

Two big winners
While the deal boosted sentiment in the Australian critical minerals space, there were two big winners in Albanese’s announcement, Arafura Rare Earths (ASX: ARU) and a joint venture between Alcoa (NYSE: AA) and Sojitz Corp (TYO: 2768).

It was a double win for Gina Rinehart-backed Arafura, which also received a letter of interest (LoI) from the Export-Import Bank of the United States (EXIM) for up to $300 million of funding for its $1.2 billion Nolans project in the Northern Territory.

“I’ve never seen this level of cooperation between the tops of two governments working together in terms of matching supply and funding. It’s actually quite historic,” Arafura managing director Darryl Cuzzubbo told MINING.com from New York, where he had just completed 12 consecutive hours of investor meetings.

“Essentially, through the agreement, Australia is giving somewhat preferential treatment to its critical minerals, to the US, and in return, the US is giving somewhat preferential treatment to funding and price mechanisms, particularly funding, both on the debt and the equity side.

“And then secondly, the agreement spells out how the process can be sped up, which will allow projects to move into construction quicker than they otherwise would,” Cuzzubbo said.

Ready to build
The Australian government announced a $100 million equity investment in Arafura’s Nolans project through Export Finance Australia.

Arafura has already invested A$60 million ($39 million) in early works at Nolans.

We’re expecting to finalize our cornerstone equity by the end of this year, and that allows us to then finalize the rest of the funding early next year and then move into construction early next year,” Cuzzubbo said.

Nolans has a three-year construction period and a two-year ramp-up phase. Once in full production, it will produce 4,440 tonnes per annum (tpa) of neodymium-praseodymium, 573tpa of mixed middle-heavy rare earths oxide and 5144,393tpa of phosphoric acid.

“You’ve got Korea, the US and Germany trying to diversify away from China. At the same time, demand is doubling,” Cuzzubbo said.

“Then you look at the rare earths supply pipeline, the number of projects that can move into construction, there’s not too many projects that are going to move into production in the next five to 10 years.”


DC is hitting the nail on the head with the last four paragraphs......really well done.
 
"
“We’re expecting to finalize our cornerstone equity by the end of this year, and that allows us to then finalize the rest of the funding early next year and then move into construction early next year,” Cuzzubbo said.

Nolans has a three-year construction period and a two-year ramp-up phase. Once in full production, it will produce 4,440 tonnes per annum (tpa) of neodymium-praseodymium, 573tpa of mixed middle-heavy rare earths oxide and 5144,393tpa of phosphoric acid.

“You’ve got Korea, the US and Germany trying to diversify away from China. At the same time, demand is doubling,” Cuzzubbo said.

“Then you look at the rare earths supply pipeline, the number of projects that can move into construction, there’s not too many projects that are going to move into production in the next five to 10 years.”"
 